Description: Rehabilitation of the Transportation Center including painting, which hasn't been repainted in over 15 years.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Commerce
Zip Code 90040
 
Senate District
34
Assembly District 50
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MARTIN GOMBERT (323) 887-4419   MARTING@CI.COMMERCE.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$45 $0 $45
Non-bond Funding
State/Federal*
$45 $0 $45
 
Total**** $90 $0 $90

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$90 $0 $90 $45 $45 $45
 
Total* $90 $0 $90 $45 $45 $45

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/01/2011 

07/06/2011 
 

 
03/01/2011 

07/06/2011 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/06/2011 

08/08/2011 
 

 
07/06/2011 

08/08/2011 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/06/2011 

10/31/2011 
 

09/02/2014 
09/06/2011 

09/01/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
10/31/2011 

12/31/2011 
09/02/2014 

09/02/2014 
09/01/2012 

06/01/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 10 10

Bond Funding Cost
Adopted:
$45,000
Current Approved:
$45,000
Actual Expenditures:
$45,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31