Real-Time Next Bus Arrival Information System

Description: Design, develop, and install a real-time bus arrival information system that uses ITS technology to disseminate the "next bus" information to transit riders.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Culver City
Zip Code 90232
 
Senate District
26
Assembly District 47
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JANE LEONARD (310) 253-6523   JANE.LEONARD@CULVERCITY.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $37 $37
PTMISEA-99314
$504 $0 $504
Non-bond Funding
State/Federal*
$2,018 $-5 $2,013
Local**
$0 $0 $0
 
Total**** $2,522 $32 $2,554

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,522 $32 $2,554 $2,554 $2,554 $0
 
Total* $2,522 $32 $2,554 $2,554 $2,554 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/11/2011 

02/01/2012 
 

 
11/11/2011 

02/01/2012 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2012 

10/01/2013 
02/28/2017 

02/28/2017 
01/01/2016 

09/01/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2013 

06/30/2014 
06/04/2019 

03/05/2020 
12/01/2018 

06/01/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2014 

06/30/2015 
03/05/2020 

04/20/2023 
06/01/2020 

06/30/2023 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5

Bond Funding Cost
Adopted:
$504,000
Current Approved:
$504,000
Actual Expenditures:
$504,000

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31