Rehabiliatation of the Mariposa County Maintenance Yard

Description: Rehabiliatation of the Mariposa County Maintenance Yard

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Mariposa
City Mariposa
Zip Code 95338
 
Senate District
14
Assembly District 25
Congressional District 19
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  50    50  
Reduced Operating/Maintenance Cost  35    35  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MARK DVORAK (209) 966-5356   MDVORAK@MARIPOSACOUNTY.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$3 $-3 $0
PTMISEA-99313
$381 $-106 $275
PTMISEA-99314
$4 $-4 $0
Non-bond Funding
 
Total**** $388 $-113 $275

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$388 $-113 $275 $275 $275 $0
 
Total* $388 $-113 $275 $275 $275 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/01/2019 

04/01/2019 
 

 
03/01/2019 

04/01/2019 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2019 

05/31/2019 
 

 
04/01/2019 

05/31/2019 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2019 

08/31/2019 
02/01/2021 

02/01/2021 
03/01/2020 

11/30/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2019 

12/31/2019 
02/01/2021 

02/01/2021 
11/30/2020 

12/31/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50 50
Reduced Operating/Maintenance Cost 35 35

Bond Funding Cost
Adopted:
$388,110
Current Approved:
$275,353
Actual Expenditures:
$275,353

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31