Replace Pressure Washer/Steam Cleaner

Description: Purchase aPressure Washer/Steam Cleaner

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Mariposa
City Mariposa
Zip Code 95338
 
Senate District
14
Assembly District 25
Congressional District 19
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20    20  
Reduced Operating/Maintenance Cost  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MIKE HEALY (209) 966-5356   MHEALY@MARIPOSACOUNTY.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$8 $0 $8
Non-bond Funding
 
Total**** $8 $0 $8

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8 $0 $8 $8 $8 $0
 
Total* $8 $0 $8 $8 $8 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2021 

05/31/2021 
 

 
03/01/2021 

05/31/2021 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2021 

06/30/2021 
 

 
06/01/2021 

06/30/2021 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20 20
Reduced Operating/Maintenance Cost 10 10

Bond Funding Cost
Adopted:
$7,646
Current Approved:
$7,646
Actual Expenditures:
$7,646

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31