Placentia Rail Station

Description: Add a new station that will alleviate the overcrowding that currently exists at the Fullerton Metrolink Station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Orange
Zip Code 92863
 
Senate District
29
Assembly District 55
Congressional District 40
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
LORA CROSS (714) 560-5788   LCROSS@OCTA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$400 $0 $400
Non-bond Funding
State/Federal*
$10,500 $0 $10,500
Local**
$12,520 $0 $12,520
 
Total**** $23,420 $0 $23,420

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$720 $0 $720 $0 $0 $720
Design(PS&E)
$2,500 $0 $2,500 $400 $400 $2,100
Right of Way
$3,500 $0 $3,500 $0 $0 $3,500
Construction
$16,700 $0 $16,700 $0 $0 $16,700
 
Total* $23,420 $0 $23,420 $400 $400 $23,020

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2006 

10/31/2013 
 

 
12/01/2006 

10/31/2013 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/14/2009 

05/30/2013 
 

 
05/14/2009 

05/30/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
11/01/2008 

03/01/2010 
 

09/02/2015 
11/01/2008 

07/31/2016 
100   

 


Begin Construction Phase

End Construction Phase
01/30/2014 

06/30/2015 
09/02/2015 

09/02/2015 
02/01/2017 

09/28/2018 
 

 


Begin Closeout Phase

End Closeout Phase
06/30/2015 

12/30/2015 
09/02/2015 

09/02/2015 
09/28/2018 

02/28/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10 10

Bond Funding Cost
Adopted:
$400,000
Current Approved:
$400,000
Actual Expenditures:
$400,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31