Caltrans Logo

Placentia Avenue Grade Separation

Description: Placentia Avenue Grade Separation between Crother Ave and Fender Ave

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Orange
Zip Code 92863
 
Senate District
29
Assembly District 55, 65
Congressional District 40
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10      
Reduced Emissions  20      
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOE TOOLSON (714) 560-5406   JTOOLSON@OCTA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$642 $4,546 $5,188
PTMISEA-99314
$11,358 $1,252 $12,609
Non-bond Funding
Local**
$55,284 $0 $55,284
 
Total**** $67,284 $5,798 $73,082

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$4,328 $0 $4,328 $4,328 $4,328 $0
Right of Way
$19,410 $0 $19,410 $19,410 $19,410 $0
Construction
$43,546 $5,798 $49,344 $49,344 $49,344 $0
 
Total* $67,284 $5,798 $73,082 $73,082 $73,082 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/2001 

05/15/2001 
 

 
05/01/2001 

05/15/2001 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/29/2009 

06/30/2010 
 

 
01/29/2009 

06/30/2010 
100   

 


Begin Right of Way Phase

End Right of Way Phase
09/09/2009 

03/16/2011 
 

 
09/09/2009 

03/16/2011 
100   

 


Begin Construction Phase

End Construction Phase
07/25/2011 

07/01/2014 
 

09/17/2013 
07/25/2011 

11/01/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2014 

07/01/2017 
09/17/2013 

09/04/2014 
11/01/2014 

11/01/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10
Reduced Emissions 20
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$12,000,000
Current Approved:
$17,797,758
Actual Expenditures:
$17,797,758

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31