Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Diesel-Electric Hybrid Articulated Buses for Rapid Service |
Description: Procurement of diesel-electic hybrid, low-floor, dual-side door 60' articulated buses for East Bay Bus Rapid Transit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda |
City | Oakland |
Zip Code | 94612 |
Senate District |
07, 09, 10 |
Assembly District | 11, 14, 16, 18, 20 |
Congressional District | 07, 09, 13 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 35 | 15 |
Increased Ridership | 35 | 18 |
Reduced Emissions | 20 | 50 |
Reduced Operating/Maintenance Cost | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
KATE MILLER | (510) 891-4859 | KMILLER@ACTRANSIT.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $330 | $330 | ||||
PTMISEA-99313 |
$5,040 | $3,100 | $8,140 | ||||
PTMISEA-99314 |
$19,170 | $-18,282 | $888 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,745 | $125,963 | $128,708 | ||||
Local** |
$2,745 | $125,541 | $128,285 | ||||
Total**** | $29,700 | $236,651 | $266,351 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$29,700 | $236,651 | $266,351 | $266,351 | $266,351 | $0 | |
Total* | $29,700 | $236,651 | $266,351 | $266,351 | $266,351 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/31/2012 02/28/2015 |
08/09/2023 08/09/2023 |
01/05/2015 06/30/2021 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/01/2015 07/31/2015 |
08/09/2023 08/09/2023 |
07/01/2021 08/09/2023 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 35 | 15 |
Increased Ridership | 35 | 18 |
Reduced Emissions | 20 | 50 |
Reduced Operating/Maintenance Cost | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$24,210,051 |
Current Approved: |
$9,028,283 |
Actual Expenditures: |
$9,028,283 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31