San Leandro BART Station Terminus

Description: Expand the transit center at the San Leandro BART station to accomodate the East Bay Bus Rapid Transit terminus, additional AC Transit lines, as well as other transit services

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Oakland
Zip Code 94612
 
Senate District
07, 09, 10
Assembly District 11, 14, 16, 18, 20
Congressional District 07, 09, 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  30    20  
Increased Ridership  50    50  
Reduced Operating/Maintenance Cost  20    30  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KATE MILLER (510) 891-4859   KMILLER@ACTRANSIT.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$2,703 $-2,100 $603
Non-bond Funding
State/Federal*
$1,547 $4,667 $6,214
Local**
$0 $321 $321
 
Total**** $4,250 $2,888 $7,138

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$192 $-192 $0 $0 $0 $0
Design(PS&E)
$349 $0 $349 $349 $349 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,709 $3,080 $6,789 $6,789 $6,789 $0
 
Total* $4,250 $2,888 $7,138 $7,138 $7,138 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2012 

11/30/2012 
08/21/2014 

08/21/2014 
07/01/2014 

10/01/2014 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2012 

03/31/2013 
08/21/2014 

08/21/2014 
07/01/2014 

11/30/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2013 

02/28/2014 
02/27/2020 

02/27/2020 
07/31/2019 

05/31/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
03/01/2014 

06/30/2014 
01/15/2021 

08/13/2020 
10/01/2020 

12/31/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 30 20
Increased Ridership 50 50
Reduced Operating/Maintenance Cost 20 30

Bond Funding Cost
Adopted:
$2,703,487
Current Approved:
$603,487
Actual Expenditures:
$603,487

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31