Bus Hoists & Washers

Description: Bus hoists & washers will be replaced at 3 maintenance facilities

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Oakland
Zip Code 94612
 
Senate District
07, 09, 10
Assembly District 09, 11, 14, 16, 18, 20
Congressional District 11, 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    5  
Reduced Operating/Maintenance Cost  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KIRAN BAWA (510) 891-4835   KBAWA@ACTRANSIT.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$4,500 $8,563 $13,063
Non-bond Funding
State/Federal*
$0 $4,727 $4,727
Local**
$0 $14,411 $14,411
 
Total**** $4,500 $27,701 $32,201

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4,500 $27,701 $32,201 $30,826 $30,826 $1,376
 
Total* $4,500 $27,701 $32,201 $30,826 $30,826 $1,376

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2014 

07/31/2014 
 

08/29/2016 
01/01/2014 

04/30/2017 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2014 

07/31/2015 
 

02/11/2021 
08/01/2014 

07/31/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
08/01/2015 

10/31/2015 
02/11/2021 

08/12/2021 
10/30/2020 

12/31/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 5
Reduced Operating/Maintenance Cost 5 5

Bond Funding Cost
Adopted:
$4,500,000
Current Approved:
$13,063,024
Actual Expenditures:
$13,063,024

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31