Caltrans Logo

A & E for Park and Ride Lot in NW Antioch

Description: Contract out for the A & E for a park and ride lot in north west Antioch

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa
City Antioch
Zip Code 94509
 
Senate District
07
Assembly District 15
Congressional District 07, 10
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  2      
Increased Ridership  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TOM HARAIS (925) 754-6622   THARAIS@ECCTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$327 $0 $327
Non-bond Funding
State/Federal*
$81 $-63 $18
Local**
$0 $13 $13
 
Total**** $408 $-49 $359

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$408 $-63 $345 $345 $345 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $14 $14 $14 $14 $0
 
Total* $408 $-49 $359 $359 $359 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2012 

06/30/2014 
08/13/2014 

08/13/2014 
01/01/2013 

06/30/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2012 

06/30/2014 
08/13/2014 

08/13/2014 
07/01/2012 

06/30/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
03/31/2014 

06/30/2014 
02/28/2018 

02/28/2018 
09/30/2017 

01/31/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 2
Increased Ridership 5

Bond Funding Cost
Adopted:
$327,019
Current Approved:
$327,019
Actual Expenditures:
$327,019

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31