Local Bus Replacement

Description: Replacing 6 local diesel buses with hybrid diesel electric fuel buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Solano
City Fairfield
Zip Code 94533
 
Senate District
05
Assembly District 08
Congressional District 10
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5      
Increased Ridership  2      
Reduced Emissions  20      
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
WAYNE LEWIS (707) 434-3804   WLEWIS@FAIRFIELD.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$547 $0 $547
PTMISEA-99314
$302 $0 $302
Non-bond Funding
State/Federal*
$3,351 $-1,323 $2,028
Local**
$0 $1,302 $1,302
 
Total**** $4,200 $-21 $4,179

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$1,369 $-1,369 $0 $0 $0 $0
Construction
$2,831 $1,349 $4,179 $4,179 $4,179 $0
 
Total* $4,200 $-21 $4,179 $4,179 $4,179 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2012 

05/01/2013 
 

 
07/01/2012 

05/01/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2013 

10/31/2013 
 

09/03/2013 
07/01/2013 

08/26/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5
Increased Ridership 2
Reduced Emissions 20
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$849,200
Current Approved:
$849,200
Actual Expenditures:
$849,200

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31