Three Paratransit Vehicles |
Description: Purchase three paratransit vehicles
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Napa |
City | Napa |
Zip Code | 94559 |
Senate District |
07 |
Assembly District | 02 |
Congressional District | 01 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 18 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
MATTHEW WILCOX | (707) 259-5976 | MWILCOX@NCTPA.NET |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $1 | $1 | ||||
PTMISEA-99313 |
$192 | $40 | $232 | ||||
Non-bond Funding | |||||||
State/Federal* |
$48 | $-48 | $0 | ||||
Local** |
$0 | $9 | $9 | ||||
Total**** | $240 | $2 | $242 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$240 | $2 | $242 | $242 | $242 | $0 | |
Total* | $240 | $2 | $242 | $242 | $242 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2012 10/31/2012 |
12/16/2014 12/16/2014 |
04/19/2013 07/29/2014 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
04/01/2013 04/30/2013 |
12/16/2014 12/16/2014 |
11/01/2014 11/24/2014 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 18 |
Bond Funding Cost | |
---|---|
Adopted: |
$192,000 |
Current Approved: |
$231,968 |
Actual Expenditures: |
$231,968 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31