Caltrans Logo

LRV Propolusion System Campaign

Description: Replace propulsion sub-systems on 149 Breda LRV's (includes 5 sub-sub-systems within each sub-system), repair welding, execute equipment quality assurance inspections.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94103
 
Senate District
11
Assembly District 17, 19
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  7    5  
Increased Ridership  2    2  
Reduced Emissions  2    2  
Reduced Operating/Maintenance Cost  3    2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOEL GOLDBERG (415) 701-4499   JOEL.GOLDBERG@SFMTA.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$600 $0 $600
Non-bond Funding
State/Federal*
$0 $3,890 $3,890
 
Total**** $600 $3,890 $4,490

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$600 $3,890 $4,490 $4,490 $4,490 $0
 
Total* $600 $3,890 $4,490 $4,490 $4,490 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2015 

12/31/2016 
 

09/09/2016 
10/01/2015 

12/31/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2016 

06/30/2016 
09/09/2016 

09/09/2016 
01/31/2017 

09/30/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 7 5
Increased Ridership 2 2
Reduced Emissions 2 2
Reduced Operating/Maintenance Cost 3 2

Bond Funding Cost
Adopted:
$600,000
Current Approved:
$600,000
Actual Expenditures:
$600,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31