Description: Provide red painted lanes on Powell St and Geary St and signal enhancement timing improvements and create new car-free zone.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94103
 
Senate District
11
Assembly District 17, 19
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  15    2  
Increased Ridership  1      
Reduced Operating/Maintenance Cost  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOEL GOLDBERG (415) 701-4499   JOEL.GOLDBERG@SFMTA.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$978 $0 $978
PTMISEA-99314
$422 $-290 $131
Non-bond Funding
 
Total**** $1,400 $-290 $1,110

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,400 $-290 $1,110 $1,110 $1,110 $0
 
Total* $1,400 $-290 $1,110 $1,110 $1,110 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2015 

09/30/2015 
 

 
04/01/2015 

09/30/2015 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2015 

09/30/2015 
 

 
05/01/2015 

09/30/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2015 

06/30/2016 
03/09/2020 

03/09/2020 
10/01/2018 

06/01/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2016 

06/30/2017 
03/09/2020 

03/09/2020 
06/01/2022 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 15 2
Increased Ridership 1
Reduced Operating/Maintenance Cost 20

Bond Funding Cost
Adopted:
$1,400,000
Current Approved:
$1,109,800
Actual Expenditures:
$1,109,800

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31