Folsom St. Transit Boarding Islands

Description: Design & construct 3 transit boarding islands along Folsom St. in downtown San Francisco

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94103
 
Senate District
11
Assembly District 17, 19
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  1    1  
Increased Ridership  1    1  
Reduced Emissions  1    1  
Reduced Operating/Maintenance Cost  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOEL C. GOLDBERG (415) 701-4499   JOEL.GOLDBERG@SFMTA.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$256 $-156 $100
Non-bond Funding
 
Total**** $256 $-156 $100

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$256 $-156 $100 $100 $100 $0
 
Total* $256 $-156 $100 $100 $100 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2014 

10/31/2015 
 

 
12/01/2014 

10/31/2015 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2015 

11/30/2015 
 

 
06/01/2015 

11/30/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2016 

03/31/2017 
03/09/2020 

01/21/2021 
05/30/2019 

10/31/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2017 

12/31/2017 
01/21/2021 

01/21/2021 
11/01/2019 

05/31/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1 1
Increased Ridership 1 1
Reduced Emissions 1 1
Reduced Operating/Maintenance Cost 1 1

Bond Funding Cost
Adopted:
$255,700
Current Approved:
$99,750
Actual Expenditures:
$99,750

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31