Caltrans Logo

Elevator Safety & Reliability Upgrades

Description: Addresses high failure rates, leading to breakdowns and entrapments in elevators at Muni metro stations which can lead to passenger delays

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94103
 
Senate District
11
Assembly District 17, 19
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  1    2  
Increased Ridership  1    1  
Reduced Emissions      1  
Reduced Operating/Maintenance Cost      2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOEL GOLDBERG (415) 701-4499   JOEL.GOLDBERG@SFMTA.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99314
$2,200 $-483 $1,717
Non-bond Funding
State/Federal*
$750 $70 $820
 
Total**** $2,950 $-413 $2,537

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$216 $0 $216 $216 $216 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,734 $-413 $2,322 $2,322 $2,322 $0
 
Total* $2,950 $-413 $2,537 $2,537 $2,537 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2016 

06/30/2016 
 

 
04/01/2016 

06/30/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2016 

03/31/2020 
03/09/2020 

09/14/2023 
10/09/2017 

02/28/2024 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2020 

06/30/2020 
09/14/2023 

09/14/2023 
02/29/2024 

09/27/2024 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1 2
Increased Ridership 1 1
Reduced Emissions 1
Reduced Operating/Maintenance Cost 2

Bond Funding Cost
Adopted:
$2,200,000
Current Approved:
$1,717,431
Actual Expenditures:
$1,717,431

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31