Caltrans Logo

Bicycle Station and Locker Parking

Description: Add between 150-175 spaces in a new Bike Station and with an upgrade to existing bike racks in the paid area of the station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Various
City Oakland
Zip Code 94612
 
Senate District
13, 16
Assembly District 03, 09
Congressional District 07, 08, 09, 10, 11, 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  2      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STEVE BEROLDO (510) 464-6158   SBEROLD@BART.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$660 $-62 $598
Non-bond Funding
State/Federal*
$136 $-136 $0
Local**
$29 $403 $432
 
Total**** $825 $205 $1,030

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$825 $205 $1,030 $1,030 $1,030 $0
 
Total* $825 $205 $1,030 $1,030 $1,030 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/27/2011 

06/30/2012 
 

 
09/27/2011 

06/30/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2012 

06/30/2014 
06/24/2019 

06/24/2019 
06/30/2017 

12/30/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2014 

09/30/2014 
06/24/2019 

06/24/2019 
03/31/2018 

02/28/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 2

Bond Funding Cost
Adopted:
$659,650
Current Approved:
$598,070
Actual Expenditures:
$598,070

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31