Concord Intermodal Improvements

Description: Design, manufacture and installation/construction of a number of access improvements to the intermodal zone at the Concord BART station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa
City Oakland
Zip Code 94605
 
Senate District
07
Assembly District 14
Congressional District 11
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3    3  
Reduced Emissions  1      
Reduced Operating/Maintenance Cost  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DEIDRE HEITMAN (510) 287-4796   DHEITMA@BART.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$400 $0 $400
Non-bond Funding
Local**
$100 $5,018 $5,118
 
Total**** $500 $5,019 $5,519

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$125 $568 $693 $693 $693 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$375 $4,450 $4,825 $4,825 $4,825 $0
 
Total* $500 $5,019 $5,519 $5,519 $5,519 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/30/2012 

 
 

 
12/30/2012 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/30/2013 

10/30/2013 
09/16/2019 

09/16/2019 
10/14/2015 

12/17/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/30/2013 

12/31/2013 
09/16/2019 

09/16/2019 
02/13/2017 

01/24/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
03/30/2015 

06/30/2015 
09/16/2019 

09/16/2019 
04/30/2019 

06/30/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3 3
Reduced Emissions 1
Reduced Operating/Maintenance Cost 1 1

Bond Funding Cost
Adopted:
$400,000
Current Approved:
$400,000
Actual Expenditures:
$400,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31