Richmond Eastside Intermodal Improvements

Description: Design and installation/construction of a number of access improvements on the eastside of the Richmond BART station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa
City Oakland
Zip Code 94605
 
Senate District
09
Assembly District 15
Congressional District 11
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5    5  
Reduced Emissions  1    1  
Reduced Operating/Maintenance Cost  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DEIDRE HEITMAN (510) 287-4796   DHEITMA@BART.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$1,500 $0 $1,500
Non-bond Funding
Local**
$375 $-375 $0
 
Total**** $1,875 $-375 $1,500

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,875 $-375 $1,500 $1,500 $1,500 $0
 
Total* $1,875 $-375 $1,500 $1,500 $1,500 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2000 

02/14/2012 
 

 
10/01/2000 

02/14/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/24/2012 

09/30/2012 
 

 
02/24/2012 

09/30/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
01/30/2013 

12/30/2013 
02/22/2016 

09/04/2018 
10/05/2015 

12/18/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
12/31/2013 

03/01/2014 
09/04/2018 

09/04/2018 
12/18/2017 

02/01/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5 5
Reduced Emissions 1 1
Reduced Operating/Maintenance Cost 1 1

Bond Funding Cost
Adopted:
$1,500,000
Current Approved:
$1,500,000
Actual Expenditures:
$1,500,000

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31