Caltrans Logo

San Carlos Transit Center

Description: Enhance an existing multi-modal transit center to facilitate improved safety and connections between SamTrans fixed route bus service, Caltrain commuter rail, local shuttles and pedestrians

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Carlos
Zip Code 94070
 
Senate District
08, 11
Assembly District 12, 19, 21
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  9      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
REBECCA ARTHUR (650) 508-6368   ARTHURR@SAMTRANS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$0 $451 $451
PTMISEA-99314
$666 $871 $1,537
Non-bond Funding
State/Federal*
$3,500 $117 $3,617
Local**
$818 $-13 $805
 
Total**** $4,984 $1,426 $6,411

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$327 $0 $327 $273 $273 $54
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5,476 $1,426 $6,902 $6,137 $6,137 $765
 
Total* $4,984 $1,426 $6,411 $6,411 $6,411 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2012 

03/31/2013 
 

 
10/01/2012 

03/31/2013 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/31/2013 

08/31/2013 
 

09/10/2015 
03/31/2013 

05/31/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2014 

12/31/2014 
09/10/2015 

03/01/2019 
11/01/2015 

09/30/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2015 

06/30/2015 
03/01/2019 

03/01/2019 
10/31/2018 

03/31/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 9

Bond Funding Cost
Adopted:
$666,095
Current Approved:
$1,987,924
Actual Expenditures:
$1,987,924

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31