Replacement of Advanced Communications System |
Description: Replace aging communications and computer aided dispatch and automated vehicle location mobile equipment
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | San Carlos |
Zip Code | 94070 |
Senate District |
08, 11 |
Assembly District | 12, 19, 21 |
Congressional District | 12, 14 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 100 | 100 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
REBECCA ARTHUR | (650) 508-6368 | ARTHURR@SAMTRANS.COM |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-99314 |
$2,485 | $-554 | $1,931 | ||||
Non-bond Funding | |||||||
State/Federal* |
$8,215 | $1,833 | $10,047 | ||||
Local** |
$0 | $101 | $101 | ||||
Total**** | $10,700 | $1,379 | $12,079 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$850 | $0 | $850 | $850 | $850 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$9,850 | $1,379 | $11,229 | $11,229 | $11,229 | $0 | |
Total* | $10,700 | $1,379 | $12,079 | $12,079 | $12,079 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2011 06/30/2012 |
08/20/2013 08/20/2013 |
02/01/2011 08/30/2012 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
02/01/2013 09/30/2013 |
08/20/2013 03/01/2016 |
06/30/2013 06/30/2016 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
10/01/2013 12/31/2013 |
03/01/2016 08/31/2017 |
07/01/2016 06/30/2017 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 100 | 100 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,485,333 |
Current Approved: |
$1,930,963 |
Actual Expenditures: |
$1,930,963 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31