Replacement of Advanced Communications System

Description: Replace aging communications and computer aided dispatch and automated vehicle location mobile equipment

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Carlos
Zip Code 94070
 
Senate District
08, 11
Assembly District 12, 19, 21
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  100    100  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
REBECCA ARTHUR (650) 508-6368   ARTHURR@SAMTRANS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$2,485 $-554 $1,931
Non-bond Funding
State/Federal*
$8,215 $1,833 $10,047
Local**
$0 $101 $101
 
Total**** $10,700 $1,379 $12,079

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$850 $0 $850 $850 $850 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$9,850 $1,379 $11,229 $11,229 $11,229 $0
 
Total* $10,700 $1,379 $12,079 $12,079 $12,079 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2011 

06/30/2012 
08/20/2013 

08/20/2013 
02/01/2011 

08/30/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2013 

09/30/2013 
08/20/2013 

03/01/2016 
06/30/2013 

06/30/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2013 

12/31/2013 
03/01/2016 

08/31/2017 
07/01/2016 

06/30/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 100 100

Bond Funding Cost
Adopted:
$2,485,333
Current Approved:
$1,930,963
Actual Expenditures:
$1,930,963

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31