Loomis Transit Enhancement Project

Description: This project will enhance the transit facility with the addition of sidewalks, bike path, bike racks, bike lockers, various ADA improvements, seating, kiosk, trash receptacles, lighting & bollards.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
04
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  15    15  
Reduced Emissions  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DAVID MELKO (530) 823-4030   DMELKO@PCTPA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$101 $0 $101
Non-bond Funding
 
Total**** $101 $0 $101

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$101 $0 $101 $101 $101 $0
 
Total* $101 $0 $101 $101 $101 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2011 

06/01/2011 
 

 
06/01/2011 

06/01/2011 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2011 

05/01/2012 
 

 
11/01/2011 

05/01/2012 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2012 

10/01/2012 
 

 
08/01/2012 

10/01/2012 
 

 


Begin Closeout Phase

End Closeout Phase
11/01/2012 

12/01/2012 
12/02/2013 

12/02/2013 
12/01/2012 

08/01/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 15 15
Reduced Emissions 5 5

Bond Funding Cost
Adopted:
$101,260
Current Approved:
$101,262
Actual Expenditures:
$101,262

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31