Caltrans Logo

Transit Bus Purchase

Description: Purchase (3) Fixed Route Buses (35 ft coach); 35-person capacity; ADA compliant; Diesel Powered & match to purchase Demand Response vans.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Shasta
City Redding
Zip Code 96049
 
Senate District
02
Assembly District 04
Congressional District 02
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  3    3  
Reduced Emissions  5    5  
Reduced Operating/Maintenance Cost  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ZACH BONNIN (530) 245-7116   ZBONNIN@CI.REDDING.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$413 $67 $480
PTMISEA-99314
$22 $-6 $15
Non-bond Funding
State/Federal*
$0 $1,873 $1,873
 
Total**** $435 $1,933 $2,368

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$435 $1,933 $2,368 $2,368 $2,368 $0
 
Total* $435 $1,933 $2,368 $2,368 $2,368 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2013 

06/30/2013 
01/12/2016 

01/12/2016 
12/01/2015 

01/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2014 

10/31/2014 
10/28/2019 

04/05/2018 
02/01/2019 

06/01/2019 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 3 3
Reduced Emissions 5 5
Reduced Operating/Maintenance Cost 10 10

Bond Funding Cost
Adopted:
$435,100
Current Approved:
$495,623
Actual Expenditures:
$495,623

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31