Caltrans Logo

Farebox Systems for Ceres Buses

Description: Install new automated fareboxes on Ceres transit buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Modesto
Zip Code 95354
 
Senate District
12, 14
Assembly District 25, 26
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3    3  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MIKE COSTA (209) 525-4644   MCOSTA@STANCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$130 $25 $155
Non-bond Funding
 
Total**** $130 $26 $156

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$130 $26 $156 $156 $156 $0
 
Total* $130 $26 $156 $156 $156 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2012 

12/31/2012 
03/10/2014 

03/10/2014 
07/31/2013 

02/28/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2013 

05/31/2013 
02/26/2015 

02/26/2015 
06/01/2014 

11/01/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2013 

07/31/2013 
02/26/2015 

02/26/2015 
01/01/2015 

02/01/2015 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3 3

Bond Funding Cost
Adopted:
$130,000
Current Approved:
$154,792
Actual Expenditures:
$154,792

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31