Refurbish 1998, 2001, & 2003 Buses

Description: Refurbish 1998, 2001, & 2003 Buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Modesto
Zip Code 95353
 
Senate District
12
Assembly District 25
Congressional District
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5      
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TERRY EASLEY (209) 577-5317   TEASLEY@MODESTOGOV.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $67 $67
PTMISEA-99313
$4,931 $0 $4,931
PTMISEA-99314
$640 $0 $640
Non-bond Funding
State/Federal*
$2,152 $-876 $1,276
 
Total**** $7,723 $-809 $6,915

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$7,723 $-809 $6,915 $6,915 $6,915 $0
 
Total* $7,723 $-809 $6,915 $6,915 $6,915 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2012 

09/01/2012 
02/26/2014 

02/26/2014 
07/01/2013 

12/31/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2013 

07/01/2014 
02/26/2014 

09/05/2017 
03/31/2014 

09/01/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2014 

09/01/2014 
09/05/2017 

09/05/2017 
09/01/2019 

12/31/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$5,571,466
Current Approved:
$5,571,466
Actual Expenditures:
$5,571,466

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31