Caltrans Logo

Purchase 40' Low-Floor CNG Heavy Duty Buses

Description: Purchase 40' Low-Floor CNG Heavy Duty Buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Modesto
Zip Code 95354
 
Senate District
25
Assembly District 12
Congressional District
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  3      
Increased Ridership  3      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DORALEE BOLES (209) 525-7504   BOLESD@STANCOUNTY.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $9 $9
PTMISEA-99313
$2,390 $0 $2,390
PTMISEA-99314
$0 $0 $0
Non-bond Funding
State/Federal*
$0 $1,231 $1,231
 
Total**** $2,390 $1,240 $3,630

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,390 $1,240 $3,630 $3,630 $3,630 $0
 
Total* $2,390 $1,240 $3,630 $3,630 $3,630 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/01/2012 

06/30/2013 
 

08/20/2013 
12/01/2012 

01/31/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
12/31/2013 

04/30/2014 
03/05/2014 

08/20/2013 
06/01/2014 

09/30/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 3
Increased Ridership 3

Bond Funding Cost
Adopted:
$2,390,000
Current Approved:
$2,390,000
Actual Expenditures:
$2,390,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31