Purchase One 35 foot CNG Bus

Description: Purchase One 35 foot CNG Bus

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Porterville
Zip Code 93257
 
Senate District
18
Assembly District 34
Congressional District 21
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      258  
Increased Ridership  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RICHARD TREE (559) 782-7448   RTREEMAN@CI.PORTERVILLE.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2024
b=c-a
Current Approved
(12/31/2024
c
Bond Funding
PTMISEA-99313
$431 $0 $431
PTMISEA-99314
$34 $0 $34
Non-bond Funding
 
Total**** $465 $0 $465

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2024
b=c-a
Current Approved
(12/31/2024
c
Cost to Date**
(12/31/2024
d
Cost Forecast
(12/31/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$465 $0 $465 $465 $465 $0
 
Total* $465 $0 $465 $465 $465 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2024)
c
% Complete
(12/31/2024)
d
Schedule Forecast
(12/31/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2012 

12/01/2013 
 

 
08/01/2012 

12/01/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2014 

01/31/2014 
08/11/2014 

08/11/2014 
12/01/2013 

12/31/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 258
Increased Ridership 10

Bond Funding Cost
Adopted:
$465,000
Current Approved:
$465,000
Actual Expenditures:
$465,000

Click to view the Final Audit Report

 

Status as of December 31, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31