Caltrans Logo

Electric Bus & MicroTransit

Description: Purchase electric bus that includes WiFi/AVL to introduce a micro transit along Route 61 in Bakersfield, CA.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
14, 16
Assembly District 32, 34
Congressional District 30, 32
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    100  
Increased Ridership      100  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DENISE SAILES (661) 869-6350   DSAILES@GETBUS.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$0 $407 $407
PTMISEA-99314
$0 $416 $416
Non-bond Funding
 
Total**** $0 $825 $825

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $825 $825 $825 $825 $0
 
Total* $0 $825 $825 $825 $825 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
08/02/2019 

10/12/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
02/20/2020 

02/20/2020 
11/15/2019 

01/05/2020 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 100
Increased Ridership 100

Bond Funding Cost
Adopted:
$0
Current Approved:
$823,284
Actual Expenditures:
$823,284

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31