Caltrans Logo

Pedestrian Plaza Improvements

Description: Improvements to the pedestrian plaza of the Norwalk/Santa Fe Springs Metrolink Station.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Norwalk
Zip Code 90650
 
Senate District
30
Assembly District 57
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SUDESH PAUL (562) 929-5660   SPAUL@NORWALKCA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99314
$100 $0 $100
Non-bond Funding
State/Federal*
$0 $400 $400
 
Total**** $100 $401 $501

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$100 $401 $501 $101 $101 $400
 
Total* $100 $401 $501 $101 $101 $400

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2014 

09/01/2014 
08/28/2014 

08/28/2014 
05/01/2014 

08/01/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2014 

03/01/2015 
10/13/2015 

10/13/2015 
06/01/2015 

03/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2015 

06/01/2015 
09/02/2016 

09/02/2016 
07/01/2016 

08/01/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 20

Bond Funding Cost
Adopted:
$100,000
Current Approved:
$100,000
Actual Expenditures:
$100,000

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31