Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bus Wash Replacement |
Description: Replacement of an obsolete bus wash/dry system with an automatic, touchless, heavy-duty vehicle wash and water reclamation system.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Norwalk |
Zip Code | 90650 |
Senate District |
30 |
Assembly District | 57 |
Congressional District | |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 30 | 52 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
SUDESH PAUL | (562) 929-5660 | SPAUL@NORWALKCA.GOV |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $1 | $1 | ||||
PTMISEA-99314 |
$109 | $0 | $109 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $869 | $869 | ||||
Total**** | $109 | $871 | $979 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $435 | $435 | $7 | $7 | $427 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$109 | $436 | $545 | $103 | $103 | $442 | |
Total* | $109 | $871 | $979 | $110 | $110 | $869 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2014 06/01/2014 |
08/28/2014 08/28/2014 |
05/01/2014 08/01/2014 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2014 10/01/2014 |
10/13/2015 10/13/2015 |
06/01/2015 03/01/2016 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
11/01/2014 01/01/2015 |
10/13/2015 10/13/2015 |
04/01/2016 05/01/2016 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 30 | 52 |
Bond Funding Cost | |
---|---|
Adopted: |
$108,678 |
Current Approved: |
$108,678 |
Actual Expenditures: |
$108,678 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31