Bus Wash Replacement

Description: Replacement of an obsolete bus wash/dry system with an automatic, touchless, heavy-duty vehicle wash and water reclamation system.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Norwalk
Zip Code 90650
 
Senate District
30
Assembly District 57
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  30    52  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SUDESH PAUL (562) 929-5660   SPAUL@NORWALKCA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99314
$109 $0 $109
Non-bond Funding
State/Federal*
$0 $869 $869
 
Total**** $109 $871 $979

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $435 $435 $7 $7 $427
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$109 $436 $545 $103 $103 $442
 
Total* $109 $871 $979 $110 $110 $869

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2014 

06/01/2014 
08/28/2014 

08/28/2014 
05/01/2014 

08/01/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2014 

10/01/2014 
10/13/2015 

10/13/2015 
06/01/2015 

03/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
11/01/2014 

01/01/2015 
10/13/2015 

10/13/2015 
04/01/2016 

05/01/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 30 52

Bond Funding Cost
Adopted:
$108,678
Current Approved:
$108,678
Actual Expenditures:
$108,678

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31