Raymond Avenue Grade Separation (Construction) |
Description: Construction of the Raymond Grade Separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange |
City | Orange |
Zip Code | 92863 |
Senate District |
29, 34 |
Assembly District | 65 |
Congressional District | 39 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 10 | 10 |
Reduced Emissions | 20 | 20 |
Reduced Operating/Maintenance Cost | 5 | 5 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
ANDY MUTH | (714) 560-5408 | AMUTH@OCTA.NET |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $1,126 | $1,126 | ||||
PTMISEA-99313 |
$33,563 | $-500 | $33,063 | ||||
PTMISEA-99314 |
$18,319 | $0 | $18,319 | ||||
Non-bond Funding | |||||||
Local** |
$24,245 | $-24,245 | $0 | ||||
Total**** | $76,127 | $-23,619 | $52,507 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$4,862 | $-4,862 | $0 | $0 | $0 | $0 | |
Right of Way |
$9,729 | $-9,729 | $0 | $0 | $0 | $0 | |
Construction |
$61,536 | $-9,028 | $52,507 | $52,507 | $52,507 | $0 | |
Total* | $76,127 | $-23,619 | $52,507 | $52,507 | $52,507 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
02/10/2009 12/01/2011 |
|
02/10/2009 12/01/2011 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2012 03/01/2013 |
|
01/01/2012 03/01/2013 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
03/01/2012 07/31/2013 |
08/21/2014 |
11/01/2012 07/31/2013 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
12/09/2013 10/18/2016 |
08/21/2014 08/21/2014 |
03/31/2014 08/31/2018 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
10/18/2016 06/13/2017 |
08/21/2014 02/03/2021 |
11/30/2018 05/31/2021 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 10 | 10 |
Reduced Emissions | 20 | 20 |
Reduced Operating/Maintenance Cost | 5 | 5 |
Bond Funding Cost | |
---|---|
Adopted: |
$51,881,535 |
Current Approved: |
$51,381,535 |
Actual Expenditures: |
$51,381,535 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31