Goldenwest Surface Lot

Description: Develop an adjacent lot that would provide an additional 193 parking spaces to the exisitng lot which currently contains 124 spaces at the Goldenwest Transportation Center

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Orange
Zip Code 92863
 
Senate District
34
Assembly District 72
Congressional District 48
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  8      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JIM KRAMER (714) 560-5866   JKRAMER@OCTA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $8 $8
PTMISEA-99314
$1,200 $0 $1,200
Non-bond Funding
State/Federal*
$900 $-900 $0
Local**
$0 $1,024 $1,024
 
Total**** $2,100 $132 $2,232

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$15 $-15 $0 $0 $0 $0
Design(PS&E)
$135 $-135 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,950 $282 $2,232 $2,232 $2,232 $0
 
Total* $2,100 $132 $2,232 $2,232 $2,232 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2010 

04/30/2012 
 

 
01/01/2010 

04/30/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/20/2011 

10/14/2013 
 

08/22/2014 
06/20/2011 

03/18/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/25/2014 

07/22/2014 
02/17/2015 

03/01/2016 
12/01/2014 

09/30/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
07/22/2014 

10/22/2014 
06/24/2016 

06/24/2016 
04/01/2016 

07/31/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 8

Bond Funding Cost
Adopted:
$1,200,000
Current Approved:
$1,200,000
Actual Expenditures:
$1,200,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31