Caltrans Logo

Purchase of Rolling Stock

Description: Purchase of seven CNG replacement buses.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Corona
Zip Code 92882
 
Senate District
37
Assembly District 71
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20    25  
Increased Ridership  17      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BRIAN CHAMPION (951) 279-3763   BRIANC@CI.CORONA.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$4 $21 $25
PTMISEA-99313
$906 $203 $1,109
PTMISEA-99314
$64 $15 $79
Non-bond Funding
State/Federal*
$775 $1,246 $2,021
Local**
$51 $0 $51
 
Total**** $1,800 $1,485 $3,285

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,800 $1,485 $3,285 $3,285 $3,285 $0
 
Total* $1,800 $1,485 $3,285 $3,285 $3,285 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2013 

06/01/2014 
10/16/2015 

03/06/2016 
05/01/2015 

02/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2014 

12/01/2014 
03/06/2016 

09/21/2016 
02/01/2016 

10/01/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20 25
Increased Ridership 17

Bond Funding Cost
Adopted:
$974,121
Current Approved:
$1,187,939
Actual Expenditures:
$1,187,939

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31