Revenue Collection Equipment/Upgrade |
Description: Custom made cover for the GFI vault that is located outside the yard. The GFI vault holds farebox revenue as well as collects and submits all ridership, revenue, and fare media information.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara |
City | Santa Barbara |
Zip Code | 93458 |
Senate District |
19 |
Assembly District | 35 |
Congressional District | |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 5 | 5 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
AUSTIN O'DELL | (805) 925-0951 X480 | AODELL@CI.SANTA-MARIA.CA.US |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$10 | $3 | $13 | ||||
Non-bond Funding | |||||||
Total**** | $10 | $3 | $13 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $2 | $2 | $-2 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$10 | $3 | $13 | $6 | $6 | $7 | |
Total* | $10 | $3 | $13 | $9 | $9 | $4 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/2013 06/30/2013 |
|
06/01/2016 06/30/2016 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2013 08/01/2013 |
|
06/01/2016 04/01/2018 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/01/2013 10/01/2013 |
04/30/2019 04/30/2019 |
05/01/2018 10/30/2018 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
11/01/2013 11/30/2013 |
04/30/2019 04/30/2019 |
01/01/2019 02/01/2019 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 5 | 5 |
Bond Funding Cost | |
---|---|
Adopted: |
$10,000 |
Current Approved: |
$8,901 |
Actual Expenditures: |
$8,901 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31