Caltrans Logo

Transit Facility Updates/Upgrades

Description: Various updates including phone system and lighting in transit facilities.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City Santa Barbara
Zip Code 93458
 
Senate District
19
Assembly District 35
Congressional District
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
AUSTIN O'DELL (805) 925-0951 X480   AODELL@CI.SANTA-MARIA.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$61 $-4 $57
Non-bond Funding
 
Total**** $61 $-4 $58

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$61 $-4 $58 $57 $57 $1
 
Total* $61 $-4 $58 $57 $57 $1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2014 

01/01/2015 
03/19/2015 

03/19/2015 
11/01/2014 

12/01/2014 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/15/2015 

03/01/2015 
 

 
02/15/2015 

03/01/2015 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2014 

03/01/2014 
03/19/2015 

03/19/2015 
04/01/2015 

06/01/2015 
33   

 


Begin Closeout Phase

End Closeout Phase
04/01/2014 

05/01/2014 
03/25/2016 

03/25/2016 
05/01/2016 

06/30/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 10

Bond Funding Cost
Adopted:
$61,272
Current Approved:
$56,773
Actual Expenditures:
$56,773

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31