Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Transit Facility Updates/Upgrades |
Description: Various updates including phone system and lighting in transit facilities.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara |
City | Santa Barbara |
Zip Code | 93458 |
Senate District |
19 |
Assembly District | 35 |
Congressional District | |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 10 | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
AUSTIN O'DELL | (805) 925-0951 X480 | AODELL@CI.SANTA-MARIA.CA.US |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $1 | $1 | ||||
PTMISEA-99313 |
$61 | $-4 | $57 | ||||
Non-bond Funding | |||||||
Total**** | $61 | $-4 | $58 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$61 | $-4 | $58 | $57 | $57 | $1 | |
Total* | $61 | $-4 | $58 | $57 | $57 | $1 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/01/2014 01/01/2015 |
03/19/2015 03/19/2015 |
11/01/2014 12/01/2014 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/15/2015 03/01/2015 |
|
02/15/2015 03/01/2015 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
02/01/2014 03/01/2014 |
03/19/2015 03/19/2015 |
04/01/2015 06/01/2015 |
33 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
04/01/2014 05/01/2014 |
03/25/2016 03/25/2016 |
05/01/2016 06/30/2016 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 10 | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$61,272 |
Current Approved: |
$56,773 |
Actual Expenditures: |
$56,773 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31