Bus Stop Improvements

Description: bus stop improvements including shelters, schedule panels, benches, trash recepticles, lighting, pads, poles, signs, etc.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City Santa Barbara
Zip Code 93458
 
Senate District
19
Assembly District 35
Congressional District
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    5  
Increased Ridership  10      
Reduced Operating/Maintenance Cost  15    15  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
AUSTIN O'DELL (805) 925-0951 X480   AODELL@CI.SANTA-MARIA.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $3 $3
PTMISEA-99313
$115 $-0 $115
Non-bond Funding
 
Total**** $115 $3 $118

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$115 $3 $118 $118 $118 $0
 
Total* $115 $3 $118 $118 $118 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/30/2014 

05/30/2014 
03/20/2017 

03/20/2017 
09/01/2017 

10/15/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2014 

06/30/2014 
07/30/2018 

07/30/2018 
12/15/2017 

01/10/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 5
Increased Ridership 10
Reduced Operating/Maintenance Cost 15 15

Bond Funding Cost
Adopted:
$115,000
Current Approved:
$114,863
Actual Expenditures:
$114,863

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31