Emergency Generator

Description: Purchase a back-up generatorat the Maint & Op building to address safety and functionality during power outages. This will prevent damaged equipment, ruined goods, lost revenue and diminished safety.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City Santa Maria
Zip Code 93458
 
Senate District
19
Assembly District 35
Congressional District 24
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  100    100  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
AUSTIN O'DELL (805) 925-0951   AODELL@SANTAMARIA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$10 $7 $17
PTMISEA-99313
$80 $-17 $63
Non-bond Funding
 
Total**** $90 $-10 $80

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $5 $5 $-5
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$90 $-10 $80 $75 $75 $5
 
Total* $90 $-10 $80 $80 $80 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2017 

07/01/2017 
 

 
05/01/2017 

07/01/2017 
100   

 


Begin Right of Way Phase

End Right of Way Phase
07/01/2017 

08/01/2017 
 

 
07/01/2017 

08/01/2017 
100   

 


Begin Construction Phase

End Construction Phase
08/30/2017 

09/30/2017 
04/30/2019 

04/17/2020 
02/15/2019 

10/30/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2018 

02/28/2018 
08/28/2020 

08/28/2020 
07/15/2020 

08/10/2020 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 100 100

Bond Funding Cost
Adopted:
$89,588
Current Approved:
$62,893
Actual Expenditures:
$62,893

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31