Safety Improvement in Ventura County

Description: Provide lighting improvements at the East Ventura layover facility. Regrade and install new asphalt and striping for the Moorpark layover facility.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura
City Ventura
Zip Code 93003
 
Senate District
27
Assembly District 38
Congressional District 23
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  1      
Reduced Operating/Maintenance Cost  1    40  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JUDITH JOHNDUFF (805) 642-1591   JJOHNDUFF@GOVENTURA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2024
b=c-a
Current Approved
(12/31/2024
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$0 $37 $37
Non-bond Funding
State/Federal*
$0 $160 $160
 
Total**** $0 $197 $197

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2024
b=c-a
Current Approved
(12/31/2024
c
Cost to Date**
(12/31/2024
d
Cost Forecast
(12/31/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $37 $37 $-37
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $197 $197 $160 $160 $37
 
Total* $0 $197 $197 $197 $197 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2024)
c
% Complete
(12/31/2024)
d
Schedule Forecast
(12/31/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2018 

 
 

 
07/01/2018 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2018 

05/01/2019 
02/27/2020 

08/15/2023 
03/01/2020 

03/31/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2019 

12/01/2019 
08/15/2023 

08/15/2023 
04/01/2023 

06/01/2023 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1
Reduced Operating/Maintenance Cost 1 40

Bond Funding Cost
Adopted:
$0
Current Approved:
$37,061
Actual Expenditures:
$37,061

 

Status as of December 31, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31