Colusa Transit Bus Replacement

Description: Purchase five, 17-passenger, two wheelchairs, gas fueled, transit buses to replace existing buses.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Colusa
City Colusa
Zip Code 95932
 
Senate District
04
Assembly District 03
Congressional District 03
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20    20  
Increased Ridership  10      
Reduced Emissions  10      
Reduced Operating/Maintenance Cost  20    20  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MIKE AZEVEDO (530) 458-0471   MJAZEVEDO@COUNTYOFCOLUSA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$420 $-45 $375
Non-bond Funding
 
Total**** $420 $-45 $375

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$420 $-45 $375 $375 $375 $0
 
Total* $420 $-45 $375 $375 $375 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2014 

04/01/2501 
07/14/2015 

07/14/2015 
11/01/2014 

07/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2014 

07/01/2014 
07/14/2015 

07/14/2015 
08/01/2015 

09/01/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20 20
Increased Ridership 10
Reduced Emissions 10
Reduced Operating/Maintenance Cost 20 20

Bond Funding Cost
Adopted:
$419,962
Current Approved:
$375,341
Actual Expenditures:
$375,341

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31