Caltrans Logo

Data Communication - Intellegent Transportation Systems Phase I

Description: Purchase data management software that will be used to monitor daily operational activities.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Norwalk
Zip Code 90650
 
Senate District
30
Assembly District 57
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    15  
Increased Ridership  10    10  
Reduced Operating/Maintenance Cost  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SUDESH PAUL (562) 929-5660   SPAUL@NORWALKCA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99314
$88 $-12 $75
Non-bond Funding
 
Total**** $88 $-12 $75

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $75 $75 $-75
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$88 $-12 $75 $0 $0 $75
 
Total* $88 $-12 $75 $75 $75 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
03/03/2016 

10/02/2018 
01/01/2016 

06/01/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2014 

10/01/2014 
03/23/2015 

03/23/2015 
07/01/2015 

09/01/2015 
 

 


Begin Closeout Phase

End Closeout Phase
03/01/2015 

04/01/2015 
03/26/2018 

10/02/2018 
05/01/2018 

07/01/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 15
Increased Ridership 10 10
Reduced Operating/Maintenance Cost 5 5

Bond Funding Cost
Adopted:
$87,637
Current Approved:
$75,252
Actual Expenditures:
$75,252

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31