(6) Mid-size Sedans for Transit (Support Vehicles)

Description: Mid-size sedans to support daily transit activities including use relief vehicles to change drivers without affecting service.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Norwalk
Zip Code 90650
 
Senate District
30
Assembly District 57
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20      
Reduced Operating/Maintenance Cost  20    40  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SUDESH PAUL (562) 929-5660   SPAUL@NORWALKCA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$200 $-3 $197
Non-bond Funding
 
Total**** $200 $-3 $197

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$200 $-3 $197 $197 $197 $0
 
Total* $200 $-3 $197 $197 $197 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2014 

06/01/2014 
01/17/2017 

01/17/2017 
05/01/2016 

06/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2014 

08/01/2014 
01/17/2017 

01/17/2017 
08/01/2016 

08/01/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20
Reduced Operating/Maintenance Cost 20 40

Bond Funding Cost
Adopted:
$199,943
Current Approved:
$197,299
Actual Expenditures:
$197,299

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31