Caltrans Logo

Bishop Facility Improvements

Description: Construction of the a transit maintenance and operating facility on approximately 1.5 acre parcel in Bishop.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Mono
City Bishop
Zip Code 93514
 
Senate District
01
Assembly District 25
Congressional District 25
 
Caltrans District
09
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    10  
Reduced Emissions  10    10  
Reduced Operating/Maintenance Cost  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JILL BATCHELDER (760) 872-1901   JBATCHELDER@ESTRANSIT.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99314
$46 $0 $46
Non-bond Funding
 
Total**** $46 $0 $46

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$25 $0 $25 $24 $24 $1
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$21 $0 $21 $22 $22 $-1
 
Total* $46 $0 $46 $46 $46 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2014 

07/01/2015 
09/29/2015 

09/29/2015 
04/01/2014 

03/01/2015 
10   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2015 

10/01/2016 
09/29/2015 

09/29/2015 
07/01/2015 

08/01/2015 
 

 


Begin Closeout Phase

End Closeout Phase
01/01/2017 

06/01/2017 
09/29/2015 

09/29/2015 
08/01/2015 

08/01/2015 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 10
Reduced Emissions 10 10
Reduced Operating/Maintenance Cost 10 10

Bond Funding Cost
Adopted:
$45,925
Current Approved:
$45,925
Actual Expenditures:
$45,925

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31