Coachella Valley Passenger Rail Project

Description: Support a service development plan required to obtain federal funding for expanded rail service to the Coachella Valley. The funds will be used to increase the frequency of Amtrak rail service.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code 92501
 
Senate District
31, 37
Assembly District 64, 65
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SHELDON PETERSON (951) 787-7928   SPETERSON@RCTC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$4,200 $-2,277 $1,923
Non-bond Funding
State/Federal*
$155,000 $-155,000 $0
Local**
$800 $-800 $0
 
Total**** $160,000 $-158,077 $1,923

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$155,800 $-155,800 $0 $0 $0 $0
Design(PS&E)
$1,500 $-1,500 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,700 $-777 $1,923 $1,923 $1,923 $0
 
Total* $160,000 $-158,077 $1,923 $1,923 $1,923 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2014 

06/01/2014 
 

 
01/01/2014 

06/01/2014 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2014 

10/01/2015 
 

 
08/01/2014 

10/01/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2015 

02/01/2017 
 

 
11/01/2015 

02/01/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2017 

06/30/2017 
11/30/2020 

11/30/2020 
10/20/2020 

11/17/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 5

Bond Funding Cost
Adopted:
$4,200,000
Current Approved:
$1,923,476
Actual Expenditures:
$1,923,476

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31