Caltrans Logo

Transit Enhancements

Description: Transit Center improvements, pedestrian and bicycle ways and bus stop improvements to enhance passenger amenities.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City San Bernardino
Zip Code 92411
 
Senate District
32
Assembly District 47
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      10  
Increased Ridership  3      
Reduced Operating/Maintenance Cost      10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ANNA RAHTZ (909) 379-7256   ANNA.RAHTZ@OMNITRANS.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $8 $8
PTMISEA-99313
$300 $743 $1,043
PTMISEA-99314
$0 $237 $237
Non-bond Funding
State/Federal*
$1,400 $-1,400 $0
 
Total**** $1,700 $-413 $1,287

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,700 $-413 $1,287 $1,287 $1,287 $0
 
Total* $1,700 $-413 $1,287 $1,287 $1,287 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

02/28/2020 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2014 

06/30/2016 
 

08/11/2022 
10/01/2020 

04/01/2021 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2016 

09/30/2016 
02/27/2023 

02/27/2023 
05/02/2023 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10
Increased Ridership 3
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$300,000
Current Approved:
$1,279,648
Actual Expenditures:
$1,279,648

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31