San Bernardino Transit Center

Description: Construction of 22 bus bays including signage, crosswalks, safety guardrails, site grading and landscaping.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City San Bernardino
Zip Code 92411
 
Senate District
32
Assembly District 47
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      30  
Increased Ridership  3      
Reduced Emissions      10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ANNA RAHTZ (909) 379-7256   ANNA.RAHTZ@OMNITRANS.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $3 $3
PTMISEA-99313
$3,406 $0 $3,406
Non-bond Funding
 
Total**** $3,406 $3 $3,409

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,406 $3 $3,409 $3,409 $3,409 $0
 
Total* $3,406 $3 $3,409 $3,409 $3,409 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/10/2011 

10/29/2012 
 

 
05/10/2011 

10/29/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2012 

08/27/2013 
 

 
11/01/2012 

08/27/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
11/01/2012 

12/01/2013 
 

 
11/01/2012 

12/01/2013 
100   

 


Begin Construction Phase

End Construction Phase
12/15/2013 

05/01/2015 
 

10/21/2015 
12/15/2013 

10/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
07/31/2015 

09/30/2015 
08/19/2020 

08/19/2020 
05/31/2020 

06/01/2020 
75   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 30
Increased Ridership 3
Reduced Emissions 10

Bond Funding Cost
Adopted:
$3,406,336
Current Approved:
$3,406,336
Actual Expenditures:
$3,406,336

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31