Caltrans Logo

Bus Shelters, Amenities, and Solar Lighting

Description: Purchase and installation of new shelters, pads, benches, signage, solar lighting, and other bus stop amenities.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Hesperia
Zip Code 92345
 
Senate District
21
Assembly District 33
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  2    2  
Increased Ridership  4    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KEVIN KANE (760) 948-4330   KKANE@VVTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$115 $0 $115
Non-bond Funding
State/Federal*
$136 $0 $136
 
Total**** $251 $2 $252

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$251 $2 $252 $117 $117 $136
 
Total* $251 $2 $252 $117 $117 $136

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/15/2014 

05/31/2014 
03/23/2015 

03/23/2015 
03/15/2015 

04/30/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
12/31/2014 

03/31/2015 
02/27/2017 

02/27/2017 
10/20/2016 

12/31/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 2 2
Increased Ridership 4 5

Bond Funding Cost
Adopted:
$115,000
Current Approved:
$115,000
Actual Expenditures:
$115,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31