City of Dinuba - Transit Center Construction

Description: Completely reconstruct existing metal building to include rider lobby, conference room, reception, dispatch, offices, restrooms, benches, sitting areas

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Dinuba
Zip Code 93618
 
Senate District
16, 18
Assembly District 34
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GEORGE AVILA (559) 591-5924   GAVILA@DINUBA.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$74 $55 $130
Non-bond Funding
State/Federal*
$0 $1,423 $1,423
Local**
$0 $525 $525
 
Total**** $74 $2,003 $2,078

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$74 $2,003 $2,078 $2,078 $2,078 $0
 
Total* $74 $2,003 $2,078 $2,078 $2,078 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2011 

10/01/2011 
 

 
09/01/2011 

10/01/2011 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/31/2011 

08/31/2013 
 

 
10/31/2011 

08/31/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2013 

01/31/2014 
 

 
01/01/2013 

01/31/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2014 

03/31/2014 
 

 
02/01/2014 

08/01/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10

Bond Funding Cost
Adopted:
$74,414
Current Approved:
$129,666
Actual Expenditures:
$129,666

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31