Redlands Passenger Rail Project

Description: Construction of approximately nine miles of rail improvements from the San Bernardino Transit Center to the University of Redlands. PTMISEA funding will be used to purchase three trains for the line.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City San Bernardino
Zip Code 92410
 
Senate District
32
Assembly District 47
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  100    100  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JUSTIN FORNELLI (909) 884-8276   JFORNELLI@SANBAG.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2,134 $2,134
PTMISEA-99313
$6,543 $13,151 $19,694
Non-bond Funding
State/Federal*
$0 $244,394 $244,394
Local**
$0 $110,572 $110,572
 
Total**** $6,543 $370,251 $376,794

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$100 $0 $100 $100 $100 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$6,443 $370,251 $376,694 $361,044 $361,044 $15,650
 
Total* $6,543 $370,251 $376,794 $361,144 $361,144 $15,650

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2014 

04/01/2015 
 

03/24/2016 
10/01/2014 

08/01/2017 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2015 

06/01/2017 
11/04/2015 

08/19/2021 
10/01/2016 

11/30/2021 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2017 

12/01/2017 
02/15/2022 

08/15/2022 
10/31/2022 

11/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 100 100

Bond Funding Cost
Adopted:
$6,542,602
Current Approved:
$19,693,954
Actual Expenditures:
$19,693,954

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31