Description: Purchase up to two replacement electric buses.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Gardena
Zip Code 90249
 
Senate District
25
Assembly District 51
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  30      
Reduced Emissions  100      
Reduced Operating/Maintenance Cost  74      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PAULA FAUST (310) 965-8811   PFAUST@CI.GARDENA.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $6 $6
PTMISEA-99314
$1,673 $-265 $1,408
Non-bond Funding
 
Total**** $1,673 $-259 $1,415

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,673 $-259 $1,415 $1,415 $1,415 $0
 
Total* $1,673 $-259 $1,415 $1,415 $1,415 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
08/01/2014 

10/31/2014 
03/02/2016 

03/02/2016 
02/01/2015 

03/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
11/01/2014 

11/30/2014 
09/02/2016 

09/02/2016 
12/01/2015 

06/01/2016 
75   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 30
Reduced Emissions 100
Reduced Operating/Maintenance Cost 74

Bond Funding Cost
Adopted:
$1,673,428
Current Approved:
$1,408,478
Actual Expenditures:
$1,408,478

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31