Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Purchase Two Electric Buses |
Description: Purchase up to two replacement electric buses.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Gardena |
Zip Code | 90249 |
Senate District |
25 |
Assembly District | 51 |
Congressional District | |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 30 | |
Reduced Emissions | 100 | |
Reduced Operating/Maintenance Cost | 74 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
PAULA FAUST | (310) 965-8811 | PFAUST@CI.GARDENA.CA.GOV |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $6 | $6 | ||||
PTMISEA-99314 |
$1,673 | $-265 | $1,408 | ||||
Non-bond Funding | |||||||
Total**** | $1,673 | $-259 | $1,415 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,673 | $-259 | $1,415 | $1,415 | $1,415 | $0 | |
Total* | $1,673 | $-259 | $1,415 | $1,415 | $1,415 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/01/2014 10/31/2014 |
03/02/2016 03/02/2016 |
02/01/2015 03/01/2015 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
11/01/2014 11/30/2014 |
09/02/2016 09/02/2016 |
12/01/2015 06/01/2016 |
75 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 30 | |
Reduced Emissions | 100 | |
Reduced Operating/Maintenance Cost | 74 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,673,428 |
Current Approved: |
$1,408,478 |
Actual Expenditures: |
$1,408,478 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31