Peninsula Corridor Electrification Project

Description: This project will electrify the Caltrain Corridor from San Francisco's 4th and King Caltrain Station to approximately the Tamien Caltrain Station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Carlos
Zip Code 94070
 
Senate District
08, 11, 13
Assembly District 12, 19, 21, 22, 23, 24, 27
Congressional District 08, 12, 14, 15, 16
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  51    51  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
REBECCA ARTHUR (650) 508-6368   ARTHURR@SAMTRANS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $332 $332
PTMISEA-99314
$10,775 $-2,875 $7,900
Non-bond Funding
State/Federal*
$738,000 $994,268 $1,732,268
Local**
$39,100 $403,073 $442,173
 
Total**** $787,875 $1,394,797 $2,182,673

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$8,000 $-8,000 $0 $0 $0 $0
Design(PS&E)
$53,529 $207,905 $261,434 $295,724 $295,724 $-34,290
Right of Way
$11,700 $0 $11,700 $0 $0 $11,700
Construction
$714,646 $1,194,892 $1,909,539 $1,344,034 $1,344,034 $565,505
 
Total* $787,875 $1,394,797 $2,182,673 $1,639,758 $1,639,758 $542,915

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2015 

12/31/2015 
 

03/07/2016 
01/01/2015 

06/30/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2016 

12/31/2019 
03/07/2016 

08/18/2021 
07/01/2016 

12/31/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2020 

12/31/2022 
08/18/2021 

08/18/2021 
01/31/2024 

12/31/2024 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 51 51

Bond Funding Cost
Adopted:
$10,775,382
Current Approved:
$7,900,000
Actual Expenditures:
$7,900,000

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31